Client: Killard Infrastructure

Project: Young Sewer Upgrade

Description: 800m Sewer upgrade from 300mm to 450mm

Location: Young, NSW

Duration: Ongoing (Oct 2021 – Now)

Client: FB Contracting

Project: Yass to Murrumbateman Water Line

Description: Construct 250 ductile/PVC Water line to feed Murrumbateman Reservoir

Location: Yass to Murrumbateman, NSW

Duration: 12 months (2019-20)

250mm Ductile Iron Water Main Creek Crossing

Client: FB Contracting

Project: Kooringal Sewer Upgrade

Description: 6km 250/300 PE Rising Main

Location: Wagga Wagga, NSW

Duration: 5 months (Feb – Jul 2020)

300mm Pipelay into Sewer Treatment Facility

Client: FB Contracting

Project: Potato Point Sewer Rising Main/Water Main Upgrade

Description: 12km Sewer/Water Main ranging 160-75mm PE Pipe

Location: Potato Point, NSW

Duration: 7 months (Nov 2020 – Jul 2021)

200mm Auger Bore, 13m long Road crossing

Client: FB Contracting

Project: Potato Point Sewer Rising Main/Water Main Upgrade

Description: 12km Sewer/Water Main ranging 160-75mm PE Pipe

Location: Potato Point, NSW

Duration: 7 months (Nov 2020 – Jul 2021)

Dual Step Trench Sewer & Water Line